MS Project :: You need to know these terms


Here are some useful interpretation

Duration = Actual Duration + Remaining Duration
Percent (%) Complete = Actual Duration / Duration
Work = Actual Work + Remaining Work
Percent (%) of Work Complete = Actual Work / Work

Start: At the beginning it is the baselined start, later one it will be replaced by the actual start
Finish: At the beginning it is the baselined finish, later one it will be replaced by the actual finish

Note: Remember to baseline your plan to save the original values

Best Regards

Bilal Okour

This entry was posted in MS Project. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s