MS Project 2007: How to share resource to Enterprise Resource Pool


To share resource to the ERP

  1. Step one, go to Tools ==> Resource Sharing ==> Share Resources


  2. Under On conflict with calendar or resource information, select the project file that takes precedence.
    1. Click Pool takes precedence if you want resource information in the resource pool project to override any conflicting information from the sharer project. This option is selected by default.
    2. Click Sharer takes precedence if you want resource information in the sharer project to override any conflicting information from the resource pool project.

Best Regards

Bilal Okour

This entry was posted in MS Project. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s