MS Project 2007 Server Lane: Resources’ Max Unit


Max. Units, the maximum units value specifies how much of this resource is available for this project — for example, part-time or multiples.
Saying this resource is available 100% means he is a full time resource, less than that means he is a part time resource.

For example, if you have a resource who is available 3 days a week then the Max Units for him/her is 60%. If he/she is available for the whole week then Max Units is 100%
You can enter maximum units as a percentage (50%, 100%, 300%), or as a decimal (0.5, 1, 3).

This entry was posted in MS Project. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s